Projects

Project #1

Conditioning Area of 8t Primary Line

Time: 12 months

Team: 8 people

Scope of delivery:

Vacuum Chamber & Loading / Unloading System’s Control Panel with Installation, Commissioning and Start-up

W

PLC: SIEMENS S7-1516- 3 DP/PN

W

I/O: 600 points

W

HMI: SIEMENS TP 1200

W

SCADA: WinCC Client-Server architecture

 

 

Project #2

Cake Forming 2t Primary Line

Time: 14 months

Team: 12 people

Scope of delivery:

Primary Line’s Control System Integration with Installation, Commissioning and Start-up

W

PLC: SIEMENS S7-1516- 3 DP/PN

W

I/O: 1100 points

W

SCADA: WinCC Client-Server architecture

 

 

Project #3

Syrup Mixing Line

Time: 8 months

Team: 6 people

Scope of delivery:

Syrup Mixing Line’s manufacturing & Control System Installation, Commissioning and Start-up

W

PLC: Rockwell Compact Logix 1769-L35E

W

I/O: 260 points

W

HMI: Rockwell PanelView Plus 7

W

SCADA: Wonderware Archestra Client –Server architecture

 

 